HS2 reaches 'key' milestone after completing half of tunnels between London and Birmingham

By Cesar Medina

15th May 2024 | Local News

HS2 has completed 53% of HS2 tunnel drives between Old Oak Common and Birimingham Curzon Street (credit: HS2).
HS2 has completed 53% of HS2 tunnel drives between Old Oak Common and Birimingham Curzon Street (credit: HS2).

HS2 (High Speed Rail 2) has announced that it has completed 29 miles of the new railway's bored tunnels between Birmingham and London.

The train network, supporting more than 31,000 jobs, has now completed excavation of two of its five twin-bore tunnels, with a further two well underway.

It shows progress being made on the line which is being constructed at 350 separate worksites between London and the West Midlands.

In total, high-speed trains will travel through 27.4 miles of twin-bore tunnels – or almost a fifth of the 140-mile route.

This means that HS2's fleet of tunnel boring machines (TBMs) are excavating and building a total of 54.8 miles of tunnel.

New analysis published last week shows that 29 miles – 53% – has been excavated and built so far, eclipsing the length of tunnels bored for the Crossrail line beneath London.

Each TBM operates like an underground factory, excavating the tunnels, lining them with pre-cast concrete tunnel segments, grouting them into place and moving forward at an average speed of between 12 and 16 metres per day.

Once the drives are finished, HS2 moves to the next stage of the tunnelling project when other vital features such as the cross-passages, vent shafts and portals will be completed.

This comes before the internal fit-out of railway systems including power, track and signalling which allows high-speed trains to operate.

Rail Minister Huw Merriman said: "Reaching this impressive milestone on a project of HS2's scale shows just how much momentum is behind construction of the line, which, once complete, will have a transformative impact on rail travel for generations to come.

"It's a significant achievement for the team helping deliver this railway and I'm delighted the project has now supported record numbers of new jobs, demonstrating the vital role it is playing in creating opportunities up and down the country."

Completed tunnels:

  • In March 2023, TBM 'Dorothy' completed its second drive of the one-mile Long Itchington Wood Tunnel in Warwickshire – the first tunnel to be completed on the project.
  • Earlier this year, 'Florence' and 'Cecilia' completed both drives of the 10-mile Chiltern Tunnel – the longest tunnel on the route – with the second breakthrough witnessed in March.

On-track tunnels:

  • In London, four TBMs are digging the 8.4-mile Northolt Tunnel. 'Sushila' and 'Caroline' have excavated around three miles of their five-mile route, travelling from West Ruislip on the outskirts of the capital to Green Park Way in Greenford, north-west London.
  • Two more are building a 3.4-mile section of this tunnel in the opposite direction from Victoria Road in Ealing to Green Park Way. 'Emily' has completed 0.2 miles and 'Anne' has just set off.
  • In the Midlands, 'Mary Ann' is 1.3 miles into the 3.5-mile drive of the first bore of the Bromford Tunnel between Water Orton in North Warwickshire and Washwood Heath in Birmingham. 'Elizabeth' has just started to build the second bore.

Tunnel yet to start:

  • Significant preparatory works have already been completed ahead of the formal start of the 4.5 mile Euston Tunnel between Old Oak Common and Euston stations in London.
  • The two TBMs are currently being manufactured and tested. The government is now exploring different funding mechanisms for delivery of the tunnel.

Graphic showing the progress HS2 has made with its TBMs machines (credit: HS2).

Jackie Roe, HS2's Civils Delivery Director said: "The halfway point for our tunnelling programme is a fantastic milestone, but we've still got a lot of work to do on the tunnels, including all cross passages, vent shafts and then fitting them out with the critical rail and power systems that will eventually allow trains to safely operate.

"This is a significant step towards delivering the country's new high speed railway, which will provide faster and far more reliable journeys, while almost doubling capacity on the most congested part of the West Coast Main Line."

Once complete, HS2 is meant to improve connections between London and the West Midlands, with trains running further north on existing lines.

We want to provide Ealing with more and more clickbait-free local news. To do that, we need a loyal newsletter following. Help us survive and sign up for our free weekly newsletter by clicking the link HERE.

     

New ealing Jobs Section Launched!!
Vacancies updated hourly!!
Click here: ealing jobs

Share:

Related Articles

Ten protesters from climate activist group Just Stop Oil appeared in court on Thursday afternoon, 25 July, charged with conspiracy to interfere with key national infrastrure. (Photo: Oliver Monk)
Local News

Heathrow protestors named as several await trial in police custody

Ina Rodrigues (left) died following a moped collision in Hammersmith with the rider and passenger fleeing the scene after (credit: Met Police).
Local News

WATCH: Met Police seek suspects after fatal Hammersmith hit-and-run

Sign-Up for our FREE Newsletter

We want to provide Ealing with more and more clickbait-free local news.
To do that, we need a loyal newsletter following.
Help us survive and sign up to our FREE weekly newsletter.

Already subscribed? Thank you. Just press X or click here.
We won't pass your details on to anyone else.
By clicking the Subscribe button you agree to our Privacy Policy.